Crews Continue Work on Richfield Municipal Center Parking Lot

Assistant City Manager Pam Dymtrenko updates residents on progress of city hall site.

While the new building officially opened to the public in June 2011—as neighbors know—the site itself is still being worked on. was on hand Tuesday night to update the and audience members on crews’ progress.

Completed Work

  • Permanent parking lot curbs installed;
  • Permanent parking lot storm sewer drains installed.

Pending Work

Find out what's happening in Richfieldwith free, real-time updates from Patch.

  • Sidewalks on Portland Avenue and 67th Street;
  • Landscaping in Heredia Park and parking lot;
  • Tennis court refurbishing and fencing;
  • Electric monument sign.

Postponed Work

  • Tennis court surfacing will be done in Spring 2012.

Once the parking lot is complete, the temporary lot will be torn out. The new lot is expected to be ready for use in the beginning of November 2011. A grand opening will be scheduled for the spring once the entire site is finished, while city officials are considering a “soft” opening in November once the parking lot can accommodate more people.

Find out what's happening in Richfieldwith free, real-time updates from Patch.


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here